US-NE · Neb. Rev. Stat. § 76-1607(2)(a) (delivery per § 76-1607(8)(a))

Self-storage software for Nebraska operators.

Nebraska's self-storage lien statute encoded day-by-day - first notice at D+10, sale eligibility at D+46. Neb. Rev. Stat. § 76-1607.

Nebraska lien clock

The full day-by-day clock, with statute citations.

This is the actual policy seeded for Nebraska. Every delinquent account locks in the rules that applied the day it opened — later statute updates never retroactively change a case already in flight.

US-NE / v2026.06.26

Nebraska lien timeline

Neb. Rev. Stat. § 76-1607(2)(a) (delivery per § 76-1607(8)(a))
Late fee
Operator Configured at D+10
Notice path
Notice Of Claim at D+10, then Advertisement Of Sale at D+46
Sale gate
Auction eligible at D+46 after the 7-day sale lead

Email notice requires the seeded paper-fallback evidence path before lien advance.

Nebraska lien timeline with statute citations
Day Event Operator action Citation
D+1 Grace Period Move from Current to Grace Period. Neb. Rev. Stat. §§ 76-1601 to 76-1609 (Nebraska Self-Service Storage Facilities Act, Laws 2017 LB492)
D+5 Send Courtesy Reminder Sms Email Move from Grace Period to Late. Neb. Rev. Stat. §§ 76-1601 to 76-1609 (Nebraska Self-Service Storage Facilities Act, Laws 2017 LB492)
D+10 Apply Late Fee Move from Late to Late Fee Applied; ledger action Apply Late Fee. Neb. Rev. Stat. §§ 76-1601 to 76-1609 (Nebraska Self-Service Storage Facilities Act, Laws 2017 LB492)
D+10 Notice Of Claim Move from Late Fee Applied to Notice Due; send Notice Of Claim by Verified Mail and Email; publication not required. Neb. Rev. Stat. § 76-1607(2)(a) (delivery per § 76-1607(8)(a))
D+46 Advertisement Of Sale Move from Notice Sent to Lien Pending; send Advertisement Of Sale by Commercially Reasonable Advertisement and Online Listing; hold 45 days in Notice Sent; publication not required. Neb. Rev. Stat. § 76-1607(2)(b)
D+46 Permit Auction Listing Move from Lien Pending to Auction Eligible; ledger action Permit Auction Listing. Neb. Rev. Stat. §§ 76-1601 to 76-1609 (Nebraska Self-Service Storage Facilities Act, Laws 2017 LB492)

What UnitOps does differently for Nebraska operators

Built around the Nebraska statute, not retrofitted onto generic PMS.

  • First lien notice at D+10 uses Verified Mail and Email; citation: Neb. Rev. Stat. § 76-1607(2)(a) (delivery per § 76-1607(8)(a)).
  • Cure window holds for 45 days before Lien Pending; citation: Neb. Rev. Stat. § 76-1607(2)(b).
  • Publication is not required by this policy step through Verified Mail and Email; citation: Neb. Rev. Stat. § 76-1607(2)(a) (delivery per § 76-1607(8)(a)).
  • Auction gate opens at D+46; citation: Neb. Rev. Stat. §§ 76-1601 to 76-1609 (Nebraska Self-Service Storage Facilities Act, Laws 2017 LB492).

Lien evidence packet

Built for the day you get sued.

For Nebraska cases, the packet presents the evidence trail beside the policy snapshot that was pinned when the case opened. It lists notices, delivery proof, ledger entries, photos, and state changes in chronological order. It presents records and citations only. The downloadable sample uses fictional seeded data with redacted names and a SAMPLE watermark.

Ready to run your Nebraska portfolio on UnitOps?

Sign up and you can start importing units, leases, and ledger history the same day. Bring your own payment processor. Bring your own QuickBooks.